MCAS Cherry Point, North Carolina
This project consists of gravel road and earthwork to access and construct new perimeter fencing for Cherry Point. More specifically: Placement of rip rap & #57 stone, 1900 linear wall feet of sheet piling, 22,500 CY of borrow material, 23,000 TN of ABC, 45,000 SY of fabric woven/nonwoven, 2300 LF of reinforced concrete pipe (ranging from 18"-36" diameter), 2 box culverts (6x4x50LF), 1 EA oil water separator, 2 EA vaults, 29 EA culvert grates to be fabricated, lane closure traffic control, 72,000 LBS of reinforcing steel, 1,000 CY of concrete, and all erosion control devices and seeding for 40+ AC.